Punch list template: a free list to copy, with a filled-in kitchen and bath example

Copy a free punch list template in Word, Excel or PDF, with a filled-in kitchen and bath example and the steps from walkthrough to final payment.

Start from the project management template

Run every client job from start to finish.

Use the template, free
On this page

A punch list is a written list of the small things left to finish or fix at the end of a construction or remodeling job: a paint miss, a door that rubs, a missing cover plate. Each item gets a location, a description, the trade who will fix it, a due date and a status, and it’s closed only after someone checks the fix.

For contractors and superintendents closing out a job, and property managers turning units. GoodTaco’s project management template can keep the list as tasks; more on that at the end.

What goes on a punch list template?

Eight columns cover most jobs. Copy this table into Word or Google Docs, or start from the Excel file above, which also has a date-verified column and a Late flag.

ColumnWhat goes in it
#Item number: 1, 2, 3. Never reuse one.
LocationRoom and spot: “Kitchen, left of range”
ItemWhat’s wrong, in words a stranger could find
TradeWho fixes it: tile setter, electrician, your crew
PhotoA photo number or file name
DueThe date it must be fixed by
StatusOpen, Waiting, Fixed or Verified
Verified byInitials of who checked it, and the date

The free templates from Procore, Smartsheet and Housecall Pro share the core: a description, a location, who’s responsible, a due date and a status. Procore’s also has an item number, a photo and sign-off lines. Smartsheet’s general contractor version adds an architect sign-off, and Housecall Pro’s residential one comes with more than 50 preset categories.

Keep the status to four words, because everyone has to mean the same thing by them:

  • Open: nobody has fixed it yet.
  • Waiting: it can’t be done yet. Say what for in the item: a part, the painter’s next visit, the owner’s choice.
  • Fixed: the trade says it’s done.
  • Verified: someone from your side looked and it’s right. Only this closes an item.

“Fixed” and “Verified” are different on purpose. Trades say a thing is done before it is, and the list is only as good as the check.

What does a filled-in punch list look like?

This is an example, not a real job: J-7101, a kitchen and primary bath remodel, as of Thursday, November 19, 2026. The walkthrough was Monday the 16th. There are 18 items, seven trades and your own crew. Of those 18, 2 are verified, 3 are fixed and waiting for a check, 1 is waiting on the painter and 12 are open. One is late: item 16, which is your own crew’s.

Four habits make a list like this work:

  • One fix per item. “Touch up paint” is five items if it’s in five rooms. Each one needs its own check.
  • A place a stranger can find. “Kitchen” isn’t a location. “Kitchen, above the window trim” is.
  • A photo of the problem, taken where you stand, with its number in the Photo column.
  • Your own work goes on the list too. The owner will notice if only the subcontractors’ items are on it.

Turning an apartment instead? The list works the same, with one list per unit and vendors in the Trade column. For the move-in side, see our rental property inspection checklist.

Anything new the owner asks for during the walk isn’t a punch list item. Write it up as a change order with a price and keep it off the list, or the list never closes.

How do you run a punch list walkthrough?

Walk it twice: once alone, once with the owner. Then keep the list moving.

  1. Walk it yourself first. Go through with a blank list before the owner arrives and fix what you can that day. Anything you find first is one the owner doesn’t have to find.
  2. Pick a route and keep to it. Room by room, the same direction each time, ceiling to floor. Skipping around is how items get missed.
  3. Write each item where you stand. Location, a few words, the trade, a photo. One fix per line.
  4. Read each item back to the owner so you both mean the same thing by it.
  5. Check the places nobody looks: the garage, closets, under sinks, the attic hatch.
  6. Agree the list is the list, and when you’ll walk it again.

Under AIA’s standard general conditions, leaving an item off the contractor’s list doesn’t change the contractor’s responsibility to finish all the work in the contract (A201-2017, section 9.8.2, here in the University of Wisconsin System’s copy). A missed item is still owed. Add it with the next number and a date.

Use this table as a prompt in each room:

CheckLook for
Walls and ceilingsPaint misses, drips, nail pops, dings, uneven caulk
FloorsScratches, gaps, squeaks, grout haze, floor protection residue
Doors and windowsRubbing, latching, locks, hardware, screens
Cabinets and countersDoor and drawer alignment, chips, gaps, hardware
PlumbingDrips under sinks, a running toilet, slow drains, hot and cold the right way round
ElectricalEvery switch and outlet, cover plates, flicker, fans; press Test and Reset on ground-fault (GFCI) outlets
AppliancesRun each one; check it sits level
LastCleaning, spare materials, keys and manuals handed over

Who fixes each item, and who checks it?

Give every item one trade and one date before you leave the site. An item with no name on it doesn’t get fixed.

Then send each trade only its own items. For the tile setter in J-7101, that’s three lines: item 2, item 9 and item 11, each with its photo and due date. A trade can’t act on a list of 18 with six other trades on it.

When a trade says it’s done:

  • Check it the same day. If it isn’t right, the trade hears while they’re still on site.
  • Change the status to Verified, with the checker’s initials and the date. Someone other than the person who did the work should check it; on a small crew, that’s the lead.
  • If it can’t be done yet, set it to Waiting and write what for, such as “Painter back Nov 23”. The item keeps its due date, so it still shows as late if the wait runs over.
  • Add new items as they turn up, with the next number. Don’t renumber, because photos and messages refer to the old numbers.

If you hold back part of a subcontractor’s final payment, or the owner holds your last draw, tie its release to the items being Verified. Check what your contract says first.

At the last walk, the owner reads the list and writes their name and the date under it, along with anything still open and when it will be done. The Word and PDF files have a line for it. Keep that page with the job. On a small crew, the lead signs for the contractor.

Once an item is a real repair that needs a visit after you’ve left, such as a callback under warranty, give it its own work order instead of leaving it on a closed list.

What changes on a commercial tenant improvement?

Same list, different people. A few lines from an example tenant improvement list: A-14, exit sign not lit (electrician, open); A-21, ceiling tile stained, suite 210 (ceiling sub, open); A-30, door closer won’t adjust (hardware, waiting on a part). Use this next to the example above:

On a tenant improvementWhat to do
Who writes the listCheck your contract. Under AIA’s standard form (A201, 9.8.2 and 9.8.3) the contractor submits it, and the architect inspects and can add items the list missed. Log those too
The architect’s walkKeep their item number in the Item text, such as “A-14: exit sign not lit”
Who verifiesIt may be the architect or owner’s rep. Put their initials in Verified by
Owner and tenant walksLog each walk’s items with its date
Why items waitAn inspection, owner-furnished equipment, the landlord
Back-chargesIf a sub won’t fix an item and you pay someone else, note the cost on the item. Charge it back only if the subcontract allows
Closeout papersThe specifications may require manuals, warranties and as-builts. Track them on the same list

The building department’s final inspection and certificate of occupancy are separate from the punch list, and the building department decides them. Ask early what it needs. For a bigger suite, print more pages: the printable has 25 rows.

What is substantial completion, and how does the punch list affect final payment?

Most small remodels don’t use AIA forms. Your contract may simply say the last payment, your last draw, is due when the punch list is done, or hold back a set amount until then. Read yours before the walkthrough, not after. State law can add rules about retainage and liens, so ask a construction attorney or your state’s contractor licensing board if you’re unsure. None of this is legal advice.

Some jobs use AIA’s 2017 standard general conditions (A201-2017). The clause numbers below are from its standard text, as copied in the University of Wisconsin System’s version:

TermIn plain words
Substantial completionComplete enough that the owner can use it as intended, even with items left (9.8.1)
Punch listThe contractor’s list of items to finish or correct before final payment (9.8.2)
RetainageMoney the owner holds back until the job is done. Paid on acceptance of the certificate, less unfinished work (9.8.5)
Final paymentThe last of the money. Not due until the contractor shows debts are paid (9.10.2)

When the contractor considers the work substantially complete, it submits the list (9.8.2), and the architect inspects (9.8.3). Anything not complete enough gets fixed first. The architect then issues a Certificate of Substantial Completion: a form that records the date, says who is responsible for security, utilities and insurance from then on, and sets the time to finish the items on the list (9.8.4). AIA says the form also starts the warranties (G704-2017). Final completion comes later, when the contractor hands over the finished project (AIA Contract Documents). Procore’s guide makes the practical point: items need to be fixed before the contractor asks for final payment (Procore).

How do you track a punch list in Excel or Google Sheets?

Use the Excel file above, or put these headings in row 1: #, Location, Item, Trade, Photo, Due, Status, Verified by, Date verified, Late?. That’s columns A to J. Add a dropdown for Status. In Excel, select the cells, then Data, Data Validation, set Allow to List and type Open,Waiting,Fixed,Verified in Source (Microsoft’s steps). In Google Sheets, select the cells, then Insert, Dropdown (Google’s steps). Do the same for Trade.

Copy this into J2 and down. It shows Late once the due date has passed and the item isn’t Verified:

=IF(F2="","",IF(AND(G2<>"Verified",F2<TODAY()),"Late",""))

Copy this into any empty cell to see how many items are left before final payment (16 for J-7101 on November 19):

=COUNTA(C2:C300)-COUNTIF(G2:G300,"Verified")

Paper, spreadsheet or app: which should you use for a punch list?

MethodUse it when
Paper (Word or PDF)One job, one walkthrough with the owner, and trades who like a printed sheet
Spreadsheet (Excel or Google Sheets)A few jobs, and one person keeps the list at a desk
AppSeveral jobs at once, or trades and owners keep asking where an item stands

We’d start with the printable on your next job. Move to the spreadsheet when you’re closing out two or more jobs at once. Move to an app when more of your day goes to answering “is it done yet?” than to fixing things. In any app, look for a photo on each item, one trade per item, a due date, and a status that only closes after a check.

How we researched this: in November 2026 we read AIA Contract Documents’ own pages for the Certificate of Substantial Completion, a University of Wisconsin System copy of the 2017 AIA general conditions, and the free templates from Procore, Smartsheet and Housecall Pro. The GoodTaco details come from the project management template’s own screens.

Close out a remodel with GoodTaco

J-7101 has 18 items, seven trades and an owner waiting on the last payment. In GoodTaco’s project management template it’s one project: each room is a section with a due date, and each item is a task with an owner, a due date and a status. Want a photo on each task, a Trade dropdown and a Fixed status? Ask GoodTaco in plain words:

On each task, add a photo and a Trade dropdown (Cabinet installer, Tile setter, Countertop fabricator, Electrician, Plumber, Carpenter, Painter, Our crew). Add a status called Fixed between In progress and Done.

  • Each item has an owner. Waiting asks what it’s waiting on, and My tasks lists one person’s items.
  • Overview counts what’s overdue.
  • Done records who and when, so mark it Done only after you’ve checked the fix. The client summary page copies into an email or prints for the sign-off walk.

GoodTaco is free to start. Paid plans start at $9 a month, and Pro at $49 a month includes 10 users; bigger teams talk to us about Enterprise.

If your list already lives in Excel, try our spreadsheet to app upload; no account needed, and the rows go into the app’s own built-in database.

Close out your next job from one list. Start free.

Frequently asked questions

What is a punch list in construction?

A punch list is a written list of the small items left to finish or fix at the end of a construction or remodeling job, such as a paint miss, a door that rubs or a missing cover plate. Each item has a location, a description, who will fix it, a due date and a status. Items are closed only after someone checks the fix.

What should a punch list template include?

Eight columns cover most jobs: item number, location, a description of what's wrong, the trade that fixes it, a photo, the due date, the status and who verified the fix. Use four statuses: open, waiting, fixed and verified. Add a line at the bottom for the owner's name and the date at sign-off. The free Procore, Smartsheet and Housecall Pro templates share the core: description, location, who's responsible, due date and status.

Who makes the punch list?

It depends on the contract. Under AIA's standard general conditions (A201-2017, section 9.8.2), the contractor prepares a list of items to complete or correct once it considers the work substantially complete, and the architect inspects. On small remodels, the contractor or superintendent usually writes it while walking the job with the owner. Either way, add anything the owner finds.

What is the difference between a punch list and substantial completion?

Substantial completion is the stage when the work is complete enough, under the contract documents, that the owner can use it for its intended purpose (A201-2017, section 9.8.1). The punch list is the list of items still to finish or correct after that. Substantial completion usually sets the warranty start date and who is responsible for security, utilities and insurance.

Can you hold back final payment until the punch list is done?

Usually the contract decides. In AIA's standard general conditions, the owner pays retainage once it accepts the certificate of substantial completion, adjusted for work that is incomplete (section 9.8.5), and final payment isn't due until the contractor provides proof that bills and debts are paid and, if the owner requires it, lien releases (section 9.10.2). State law may add rules, so read your contract and ask a construction attorney or your state's licensing board.

How do you make a punch list in Excel or Google Sheets?

Put these headings in row 1: number, location, item, trade, photo, due, status, verified by. Add a dropdown for status (open, waiting, fixed, verified) and one for trade. Number each item and never reuse a number. A flag column can show Late when the due date has passed and the status isn't verified. This guide's free Excel file already has all of it.

How long does the contractor have to finish a punch list?

The contract sets it. Under AIA's standard general conditions, the certificate of substantial completion fixes the time within which the contractor must finish the items on the list (section 9.8.4). Without a certificate, agree a date for the whole list at the walkthrough and give every item its own due date, so one late trade doesn't hold up the rest.

Free template

Start from the project management template

Get your own copy of a working project management app with sample records, ready to make yours. Free to start.

Use the template, free

Or turn your own sheet into an app

Keep exploring

Related guides and templates

View all articles

Guide

Project management software for consulting firms: costs

Project management software for consulting firms: what a 10-person firm pays for 8 shortlisted tools, and when a PSA suite pays off.

Template

Google Sheets budget tracker template for teams

Turn a budget spreadsheet into a Google Sheets budget tracker template, with live spend, threshold alerts, and one shared view everyone trusts.

Template

Rent roll template for Google Sheets: units, tenants, leases

A rent roll template for Google Sheets with units, tenants, lease dates and rent due. Connect it to GoodTaco for a tenant tracker your team can share.

Industry

Commercial Property Management Software for Small Teams

Build commercial property management software from the spreadsheets your team already runs — maintenance requests, unit tracking, tenant records. No credit card required.