Manufacturing work order: what goes on one, with a job traveler example

What goes on a manufacturing work order: part and revision, routing, materials, setup and run time, sign-offs and scrap. Free job traveler, with a filled-in example.

Turn your spreadsheet into an app

Upload an Excel or CSV file. Free, no account needed.

Upload a spreadsheet
On this page

A manufacturing work order is the instruction to make a set quantity of one part or product by a due date. It names the part and its revision, lists the steps in order with the work center for each, adds the materials and the time allowed, and records who did each step, the scrap and the quality check. Printed to travel with the parts, it’s called a job traveler.

This guide is for owners and production managers at job shops and small manufacturers: machine shops, fabricators, cabinet shops and print shops. It gives you every field, a filled-in traveler, what to change for CNC and cabinet work, how to number orders and what shop software costs. If your jobs live on a whiteboard or in a spreadsheet, you can put them in a GoodTaco app; the end of this guide shows how.

What goes on a manufacturing work order?

The example column is MO-2407, a run of 40 steel brackets (an invented example). For a one-off job, such as a kitchen, the quantity is 1 and the job name or address replaces the part number.

FieldExample: MO-2407
Work order numberMO-2407
Part number and revisionBRK-2210, rev C
DescriptionMounting bracket, 11 gauge steel, 2 bends
Job name or siteRidgeline Equipment, bracket run
Customer or sales orderRidgeline Equipment, PO 88213
Quantity40
Due dateNov 25, 2026
Materials4 sheets of 11 gauge steel, 80 weld nuts (3/8-16)
Operations, in orderLaser cut, press brake, weld, inspect and pack
Work center for eachLaser 1, Brake 2, Weld bay, Inspection bench
Setup and run timeSetup 0.5 hours; run 1.5 minutes per part
Operator sign-offInitials and date, on each operation
Good and scrap countsWritten on each operation
ReworkReason and hours, if a part goes back
Quality checkAgainst the drawing at rev C, or the cut list
NotesFinish, color, hardware, special handling

A few of these need a line of explanation:

  • Part number and revision. Always print the revision. A shop that cuts rev B after the drawing moved to rev C pays for the whole run twice. Print the traveler when the job is released, not weeks ahead, and pull the old one when the drawing changes.
  • Routing. The routing is the list of operations in order, each with a work center: the machine or station where it happens. Number them 10, 20, 30, so you can add an operation later (say 25) without renumbering.
  • Bill of materials. The bill of materials (BOM) is what goes into one part: raw stock, hardware and outside processing such as plating or powder coat. The order multiplies it by the quantity, so the stockroom pulls the right amount.
  • Setup and run time. Setup is the time to get the machine ready, once per job. Run is the time per part. Estimated hours = setup + (run minutes × quantity ÷ 60).
  • Scrap and rework. Count them at the operation where they happen. “Scrap 1” on operation 10 points at the cutting, not the welding.

What does a job traveler look like?

The picture above is MO-2407 on the morning of Nov 20: the laser cut and the press brake are signed off, the weld is 25 parts in and the inspection hasn’t started. Print the Word or PDF version above for a blank one. Here is where each operation’s estimate comes from:

OperationSetup + run = estimate
10 Laser cut0.5 + (40 × 1.5 ÷ 60) = 1.5 hours
20 Press brake0.75 + (40 × 1.5 ÷ 60) = 1.75 hours
30 Weld 2 nuts0.25 + (40 × 3 ÷ 60) = 2.25 hours
40 Inspect and pack0 + (40 × 1.5 ÷ 60) = 1 hour

The job is estimated at 6.5 hours. When operation 40 is signed off, write the actual hours, the scrap total and who did the quality check, then file the sheet. If actual hours came in at 7.3 against 6.5, you know to look at which operation ran long, and the next quote for 40 is better.

What changes on the traveler for your kind of shop?

The fields stay; the operations and the extra lines change. A lot is one batch of material. A first article is the first part, checked against the drawing before you run the rest.

ShopWhat to add
FabricationWhat’s above: cut, bend, weld, finish, inspect
CNC machiningProgram number and revision, fixture or vise, tools, first-article check, in-process checks
Cabinets and woodCut list, sheet goods, edge banding, assembly, finish, install date
Regulated workMaterial lot or heat number and cert, if your customer asks
Outside processingAn operation of its own: the vendor and the ship date

A cabinet shop’s work centers might be the panel saw, edgebander, CNC router, assembly bench, finish room and install. A run of 12 doors with 0.5 hours of setup and 20 minutes a door on the router is 0.5 + (12 × 20 ÷ 60) = 4.5 hours.

How is it different from a sales order or a maintenance work order?

DocumentWhat it says
Sales orderThe customer wants 40 brackets, at this price, by this date
Manufacturing work orderMake 40 brackets: these steps, these materials
Maintenance work orderFix or service the laser or the brake
Purchase orderBuy 4 sheets of steel from the supplier

A sales order starts the chain: it triggers one or more manufacturing work orders, and those trigger purchase orders for what the stockroom lacks. Put the sales order or customer PO number on the traveler. A maintenance work order sits to the side: when the brake goes down, the repair is a maintenance job and the manufacturing order waits. Our work order template has the maintenance form, and what a work order is covers the basics.

How do you number manufacturing work orders?

Use a prefix and a count from one list, such as MO-2407, so it can’t be mistaken for a purchase order or an invoice. Start at 2401 or 1001 so numbers sort in order, never reuse one and keep cancelled jobs, marked cancelled. Two shop rules:

  • Split lots keep the job number. If MO-2407 ships in two batches, call them MO-2407-A and MO-2407-B.
  • Put the number on everything: the traveler, the material tag, the cart, the packing slip and the invoice.

The board below is one week of orders, the way a whiteboard shows them: a slip for each order in a column by status.

When do a spreadsheet and a whiteboard stop working?

For a handful of jobs and one person who updates the list, they work fine, and the Excel download above is built for that. It’s time for something more when:

  1. Two lists disagree. The traveler says op 30 is done and the board says it’s waiting.
  2. You can’t answer “where is it?” Someone walks the floor to find out.
  3. Estimates never get checked. Actual hours sit on paper travelers in a drawer.
  4. You can’t see the queue. Which orders are lined up at the press brake?
  5. Revisions slip. A rev B traveler reaches the floor after the drawing moved to rev C.

What does shop software cost?

ToolPrice as listed
KatanaFree up to 30 SKUs (items you stock); Advantage is custom-priced
MRPeasy$49, $69, $99 or $149 per user a month, monthly billing
FulcrumNo price shown; offers a demo
ProShop ERPNo price shown; custom, based on users

Prices checked on each vendor’s page in November 2026. Fulcrum says it is built for precision CNC and sheet metal shops. ProShop’s pricing page speaks to precision machine shops. Katana suits product makers who track stock.

MRPeasy gives a month free on annual billing and a 15 + 15 day free trial; quality control and subcontracting start at $69. JobBOSS is another name machine shops mention.

For a 10-person shop where 6 people use the system, MRPeasy Starter billed monthly is 6 × $49 = $294 a month, or 6 × $69 = $414 on Professional. Add setup time: these systems expect every part, routing and bill of materials entered first.

Where would we look first for a 5 to 40 person shop? MRPeasy, because it’s the one you can price today, and your own 6-user number is a minute’s arithmetic. A CNC shop doing aerospace or medical work should ask Fulcrum and ProShop ERP for proposals. If you make products from stock, try Katana’s free plan. If your problem is only “nobody can find the traveler”, you may not need any of them yet.

Build your job travelers in GoodTaco

Upload the list you keep today, or the Excel tracker above, with no account needed to try. The records go into the app’s own built-in database, and you ask for the rest:

Make an app for our job shop. Each order has a number, part, revision, quantity, due date and customer. Each order has operations in order, with a work center, setup hours, run minutes per part, an operator, the date done, good and scrap counts. Add a page for each order laid out for printing as a traveler.

You’d get:

  • An order page with the part, revision, quantity, due date and customer.
  • Its operations in order, with operator, date and good and scrap counts.
  • A traveler page laid out for printing, from the same record the office sees.

A private app for your team: only the people you invite can sign in, with Google or an emailed link, before they see any data.

GoodTaco is free to start. Paid plans start at $9 a month, and Pro at $49 a month includes 10 users; bigger teams talk to us about Enterprise.

Try it with your own job list. Start free.

Frequently asked questions

What is a manufacturing work order?

It's the document that tells the shop floor to make a set quantity of one part or product by a due date. It names the part and revision, the quantity, the steps in order (the routing), the materials, and the setup and run time for each step. Operators sign off each step as they finish it, and the order records scrap, rework and the quality check.

What is a job traveler?

A job traveler is the manufacturing work order printed to travel with the parts from one work center to the next. Each step has a line for the operator to fill in: who did it, the date, how many good parts and how many scrapped. Many shops use the words traveler, job ticket and work order for the same sheet.

What is the difference between a work order and a sales order in manufacturing?

A sales order is the customer's request to buy: what they want, how many, the price and the date. A manufacturing work order is your internal instruction to make it. One sales order can lead to several work orders, for example one for each part, and the sales order number goes on each work order so the job can be traced back to the customer.

What is the difference between a manufacturing work order and a maintenance work order?

A manufacturing work order makes a product: it lists parts, materials and the steps to build them. A maintenance work order repairs or services the equipment that makes the product, such as a lathe or a press brake. They use similar fields, such as a number, a due date and a sign-off, but they are separate lists.

What should be on a production work order?

The order number, part number and revision, description, quantity, due date and customer or sales order. Then the operations in order with the work center, setup and run time, the materials with quantities, a sign-off and good and scrap counts for each step, and the quality check. A drawing or a note on special handling goes with it.

How do you number manufacturing work orders?

Use a prefix and a count from one list, such as MO-2407, and never reuse a number, even for a cancelled job. If a job is split into two lots, add a suffix such as MO-2407-A and MO-2407-B so the lots stay linked to one job. Put the number on the traveler, the material, the packing slip and the invoice.

Can I run production work orders in Excel?

Yes, for a small shop with one person keeping the list. One sheet holds the orders and a second sheet holds one line per operation, with formulas for estimated hours and the difference from actual hours. It gets hard when several people update it at once, when you need to see which orders are waiting on which work center, or when travelers on paper and the sheet disagree.

Free · no account needed

Turn your spreadsheet into an app

Upload an Excel or CSV file and we’ll build an app around your records, with its own database. Free, no account needed.

Upload a spreadsheet

No file handy? Start from a template

Keep exploring

Related guides and templates

View all articles

Guide

Maintenance request form template: fields and a sample

Copy the 10 fields a maintenance request form needs, see a filled-in tenant sample, and learn to collect and triage every request in one list.

Guide

Property maintenance software for landlords: 11 tools priced

Property maintenance software for landlords and property managers: 11 tools, with list prices at 20, 80 and 250 units and the free options.

Guide

Section 8 inspection checklist: HQS and NSPIRE for landlords

A room-by-room Section 8 inspection checklist for landlords, how NSPIRE replaces HQS by February 1, 2027, and the 24-hour and 30-day deadlines after a fail.

Industry

Supply Chain Software Built From Your Spreadsheet

Build supply chain management software from the spreadsheets your team already runs, purchase orders, vendor tracking, risk flags. No ERP migration. Deploy in minutes.